Veleton
Tbilisi, Georgia, I. Chavchavadze Avenue (A / MZ A-20 with Veleton MPC)
Tbilisi · Heavily loaded urban arterial road, bus lanes

Tbilisi, Georgia, I. Chavchavadze Avenue (A / MZ A-20 with Veleton MPC)

Necesidad

In 2021 a project began to restore I. Chavchavadze Avenue in Tbilisi. Under the design, stone mastic asphalt SMA-20 with a modified binder was used for the upper courses of the pavement.

Despite the use of SMA and modified bitumen, signs of rutting began to show on the bus lanes within a few months of the works being completed. This indicated that the solution applied was not providing sufficient resistance of the pavement to the actual service loads.

During the year the asphalt pavement on the problem sections was replaced twice, but the problem could not be resolved. Rutting continued to appear precisely in the most intensively loaded zones, on the bus lanes and the braking sections.

The main causes of the accelerated breakdown of the pavement were:

High urban traffic

Round-the-clock traffic of buses weighing from 16 tonnes

Intensive shear loads in the surface course of the pavement

Frequent braking and acceleration of public transport

Increased pressure on the pavement along the same wheel paths

Insufficient resistance of the previous solution to plastic deformation

The need for annual and repeated routine repairs

The team's task was to move away from constant repairs, to select a more resistant type of asphalt mixture and to provide a pavement able to work under intensive bus loads without rutting.

The production side of the project was a further challenge. The supplier of ready-made modified bitumen had interruptions to deliveries, so the asphalt plant had to move to modifying on its own with limited technical capability.

Solución Veleton

Modification of the asphalt mixture using the Veleton MPC polymer-composite modifier by dry addition was chosen to solve the problem.

The key decision was to change the type of pavement: instead of SMA-20 with a modified binder, type A / MZ A-20 asphalt with Veleton MPC was used on the bus lanes.

This approach made it possible not merely to replace the material but to adapt the design solution to the site's actual service conditions: high traffic, regular movement of heavy buses, braking zones and intensive shear deformation.

Three key changes were made in the project:

Changing the type of asphalt mixture from SMA-20 to type A / MZ A-20 asphalt

Using Veleton MPC by dry addition

Adapting the dosage to the most heavily loaded sections of the bus lanes

Dry addition proved the optimal solution for the asphalt plant, since it made it possible to move quickly to modifying the mixture on its own, without depending on deliveries of ready-made modified bitumen.

Veleton's technology made it possible to:

Increase the resistance of the pavement to rutting

Reduce the risk of plastic deformation in braking zones

Increase the resistance of the pavement to shear loads

Adapt the properties of the mixture to the bus lanes

Do away with constant dependence on ready-made modified bitumen

Give the asphalt plant flexibility in production

Reduce bitumen costs

Reduce the need for repeat repairs

Acciones de Veleton en obra

The Tbilisi project was carried out as a rapid deployment of the technology at a working asphalt plant.

Veleton specialists provided comprehensive support for the move to modifying on site:

Audited the asphalt plant's equipment

Assessed the technical capability of production

Identified the plant's limitations

Selected Veleton MPC for the task of rapid in-house modification

Adapted the dry addition technology to the existing equipment

Gave recommendations on the production process

Helped start modification without purchasing ready-made modified bitumen

Selected a dosing approach for the most heavily loaded sections

Supported the plant's move to working permanently with Veleton MPC

The speed of deployment was a separately important factor. The plant needed to resolve the interruptions to modified bitumen deliveries promptly and to keep road works going without stopping production.

A month after deployment the asphalt plant gave up ready-made modified bitumen entirely and moved to permanent in-house modification using Veleton MPC.

El resultado en cifras

The project produced a result both at the level of the pavement and at the level of the economics of production.

Project timeline

2021, major repair of I. Chavchavadze Avenue completed, the design solution being SMA-20 with a modified binder

A few months later, signs of rutting appearing on the bus lanes

During the year, the pavement on the problem sections replaced twice

2022, type A / MZ A-20 asphalt with Veleton MPC laid on the bus lanes

2026, no rutting or other defects on the sections with Veleton MPC

Service figures

Bus traffic: round the clock

Bus weight: from 16 tonnes

Most problematic zones: bus lanes and braking sections

Condition of the pavement as of 2026: no rutting and no visible defects

Repeat repairs after the solution was applied: not required

Production figures

Time for the asphalt plant to move to in-house modification: around 1 month

Giving up ready-made modified bitumen: complete

Reduction in bitumen costs: 14%

Stability of the asphalt plant's work: increased

The main practical result is that a section which previously needed the pavement replaced again within its first year of service now works, after Veleton MPC was applied, with no rutting appearing at all, even under round-the-clock traffic of buses weighing from 16 tonnes.

Efecto adicional

As of 2026 no rutting is observed on the bus lanes of I. Chavchavadze Avenue, there is no cracking or shear deformation, and the pavement remains in stable condition with no need for repeat repairs. It matters particularly that the result was achieved on sections where the previous solution, SMA-20 with a modified binder, did not provide the resistance required. This confirms that for heavily loaded bus lanes what is decisive is not only the presence of a modified binder but also the right choice of mixture type, asphalt structure and method of modification.

Efecto para el presupuesto

The economic effect showed at two levels. At the level of production, the asphalt plant stopped buying ready-made modified bitumen and moved to modifying on its own, cutting bitumen costs by 14% and reducing its dependence on an external supplier. At the level of road maintenance, annual routine repairs were eliminated, repeat replacements of the pavement were reduced to a minimum, and the service life between repairs was increased many times over, which considerably reduced budget costs on a problem section. The saving was achieved not by making the material cheaper but by a more precise engineering solution: changing the type of mixture, using Veleton MPC and moving to controlled in-house modification.

“After several unsuccessful attempts to solve the rutting problem on the bus lanes, we were looking for a solution that would genuinely stand up to the real loads. Using Veleton MPC allowed us not only to stabilise the pavement but also to do away with constant repairs. Today the section works with no defects, and that is the best measure of how effective the chosen solution is.”

Parámetros de la obra
Tbilisi · 2022
Type
Heavily loaded urban arterial road with bus lanes and zones of intensive braking
Problem
After the 2021 major repair with SMA-20, rutting appeared on the bus lanes twice a year; the pavement was replaced, but the problem could not be resolved
Solutions / technology
Veleton MPC, dry addition into type A / MZ A-20 asphalt
Type of mixture
Originally SMA-20 with modified binder; finally A / MZ A-20 with Veleton MPC
Result with Veleton
As of 2026 no rutting is observed, there are no pavement defects, and repeat repairs are not required
Service load
Round-the-clock traffic of buses weighing from 16 tonnes
Production effect
Within a month the asphalt plant gave up ready-made modified bitumen entirely and moved to modifying on its own
Effect on the budget
Bitumen costs fell by 14%; annual repairs were eliminated and budget costs considerably reduced
Fotos de la obra

4 fotos